Full Refurbishment for Island Refinery

The process of reopening the plant had uncovered more than 500 pumps that needed considerable refurbishment and repair. The most important of these was a critical jet pump used for hydraulic decoking. It was badly damaged and sent to the original equipment manufacturer (OEM) for inspection. The OEM recommended that the refinery replace most of the pump parts, as well as a costly repair that would require 35 weeks to rebuild.

Viable alternative

Instead, the refinery sent the pump to global aftermarket pump service provider, Hydro, Inc. in Chicago, where it was refurbished for just over half the cost of the OEM proposal. The time involved was also significantly improved to just eight weeks by using a non-destructive evaluation and rebuild process at a 46,000 ft2 facility where Hydro develops and implements engineering modifications for improving the performance of critical pumps and then verifies that performance in their Hydraulic Institute certified test lab.

Significant reopening

The original refinery opened in the mid-1960s. In the early 1970s, it was re-rated at 650,000 barrels per day. It had been one of the largest refineries in the western hemisphere, so the impact of reopening the plant would be significant. In this case, Hydro was tasked to work with the critical highenergy pump to prepare for its reopening. The new owners began the process two years ago and it is expected that the plant will be open for operation in the first quarter of 2020. Once restarted, the plant will be able to process up to 210,000 barrels per day of oil, a fraction of the 1,500- acre (607-hectare) plant’s peak capacity in the 1970s of 650,000 bpd.

When the plant was shut down, the pumps and other equipment in the refinery were either left in place or went into storage where they were kept in poor condition. Time constraints prohibited proper preventative maintenance before the refinery shut down. The tropical climate is hot, salty, humid, oppressive, and several hurricanes occurred during this time. All of these extreme conditions can contribute to the deterioration of heavy rotating equipment. Over the course of the year, the temperature typically varies from 72°F to 88°F and is rarely below 68°F or above 90°F. Continue reading

Engineering Analysis Resolves Startup Issues at Middle Eastern Plant

During the commissioning and startup of an alumina processing plant in the Middle East, a significant recurring pump issue was causing delays to the commissioning of the facility. When de-energizing the equipment, the live steam condensate vertical can pumps experienced repeated failures of all installed units. These seizures occurred at both the design fluid temperature and when pumping cold water.

Because this was a new plant in the commissioning phase, the equipment was under warranty. However, negotiations with the OEM were lengthening the challenged startup schedule. There was little insight into the root cause of the equipment failure.

As the repeated failures were affecting the plant commissioning date, the large architect, engineering and construction (AEC) firm in charge of plant commissioning decided to contact an independent, aftermarket service provider located in Dubai, United Arab Emirates, to conduct an assessment to determine the root cause of the pump failures and provide solutions.

Source: https://www.pumpsandsystems.com/engineering-analysis-resolves-startup-issues-middle-eastern-plant

Hydraulic Rerates & Pump Efficiency

During a mechanical seal replacement at a major gas plant, a reliability engineer identified that their API OH2 centrifugal pump was operating below the Minimum Continuous Stable Flow (MCSF).

In this case, Hydro Rocky Mountain partnered with HydroTex Deer Park‘s engineering team to provide the customer with an innovative solution by utilizing the existing casing and providing a redesigned impeller to optimize the overall efficiency and life cycle of the unit.

Watch as Ares Panagoulias and Glen Powell, of Hydro’s test lab, examine the historic operating conditions in regard to the pump’s best efficiency point (BEP) and provide a performance test to validate the upgrades and modifications.

Case Study: Hydraulic Rerates & Pump Efficiency from Hydro, Inc. on Vimeo.

Read the full article on World Pumps: worldpumps.com/ancillary-products/features/seal-replacement-reveals-causes-of-vibration/

Hydro Middle East performs swift re-build on fire-damaged circulating pumps

Hydro Middle East, specialists in pump rebuilding, particularly in the oil and gas industry and other industrial markets was called in to assess the damage and redesign and rebuild the fire-damaged pumps. Hydro’s engineers first evaluate the causes of any pump damage or failure and then provide expert engineering analysis and a responsive field service.

Written by: Thomas Arakal (Hydro Middle East)
Published by: World Pumps

Two fire damaged pumps

Two fire damaged pumps arrive at the Hydro Middle East Service Centre.

Analysis & recommendations

In the case of the fire-damaged pumps, once the fire was under control, Hydro immediately sent a field engineer to the site to conduct a root cause analysis and make recommendations to ensure that the equipment would be restored within the very fast turnaround that the company required.

The engineers discovered that the fire had been so severe it had completely burned out all of the oil in the bearing housing. In addition, the baseplate was also warped because of the excessive heat. A turnaround of between two and three weeks for redesign and rebuild was proposed, subject to mechanical seal availability and the two hot oil circulating pumps, along with the baseplate and the motors were shipped to Hydro Middle East’s facility in Dubai, U.A.E.

Continue reading